One Great George Street, London

9 mm Polyurethane Screed & 100 mm Radius Coving

Project Overview

HCE commissioned GSS Flooring to refurbish their catering facilities at the prestigious One Great George Street, a landmark building in central London. The objective was to upgrade the flooring system to ensure long-term durability, hygiene, and safety in a high-traffic catering environment.

Preparation Process

We used state-of-the-art diamond grinding equipment to prepare the substrate, ensuring optimal adhesion for the new flooring system. Thresholds and drain perimeters were carefully lowered with precision diamond concrete saws and specialist breaking tools to ensure the 6 mm screed finished flush.

Substrate Modifications

Surrounding concrete edges were removed where necessary, and a three-part epoxy mortar was applied and finished at a depth of exactly 6 mm below the surface level at thresholds and around drains. This ensured a smooth and seamless transition throughout the facility.

Screed Installation

Over the course of two days, 180 m² of 6 mm Polyurethane screed was laid using trowel application techniques to achieve a uniform, durable surface suitable for heavy-duty catering environments.

Finishing Touches

Once the screed was fully cured, all expansion joints were carefully reinstated using a flexible polysulfide joint compound to accommodate movement and maintain integrity over time. To enhance the longevity and ease of maintenance of the floor, a coloured roller-applied seal coat was added as the final protective layer.

The completed floor system delivered a seamless, hygienic, and highly durable solution tailored to the needs of a busy commercial kitchen.

 

Project Details

Resin System: 6 mm Polyurethane Screed & 100 mm Radius Coving
Client: HCE
Location: London
Area: 180 m2
Installation: 7 days

Downloadable PDF