MACK is a high contracted fruit and vegetable distribution centre, working 24/7, creating a tight time frame for GSS Flooring to commence work on their new forklift route. Leaving us with no choice but to use rapid curing polyespartics, allowing us to put two final coats on the aggregated system in a day to return the area back to MACK as quick as possible. 

Vacuum assisted HTC diamond grinders removed all contamination, dust and dirt from the original concrete floor, following with a roller applied moisture tolerant primer to seal the and strengthen the substrate. 

A flexible, 3mm polyurethane resin was then applied by pin rake and trowel. While the resin was still wet, a 0.8-1.2mm quartz aggregate was broadcast onto the resin to achieve the anti-slip requirement. An application of a coloured, two-part, polyespartic coating was then applied to seal the aggregates.